Data center developer offers $10M in benefits to Oakland County community

This is a gift article, originally appearing in Crain’s Detroit Business.

California developer Verrus is looking to sweeten the deal for a community in southwest Oakland County in its bid to construct a 1.8-million-square-foot data center called Project Flex that’s targeting California-based Anthropic, the maker of Claude, as its end user.

Verrus is offering Lyon Township $10 million in funds for the community to administer, as well as other benefits, as a part of a community-benefits framework it is asking the board of trustees to approve on Monday night.

The request for a benefits agreement came in writing to the board on June 7, but Verrus has not yet received a response. The township’s planning commission was set to vote on the final site plan for the data center on July 13, but Verrus requested to be removed from the agenda and the meeting has been canceled, according to Lyon Township Planning Coordinator Jenny Moule.

The framework includes: a $5 million community fund for parks, recreation, environmental improvements and a community project of the township’s choosing; $2 million for fire services, EMS support, hazmat response and emergency preparedness; and $3 million toward local schools and workforce training.

Verrus’ offer also includes commitments to host a local job fair, awards for local and regional contractors and coordination on sound and lighting standards.

The project is expected to create $300 million in tax revenue for the community over 17 years and create 210 permanent jobs.

“Project Flex was designed from the beginning to be a good neighbor, and that includes going beyond what the zoning requires to invest meaningfully in the Lyon Township community,” Jeff Bladen, head of energy at Verrus, said in a statement. “We put this proposal on the table months ago in good faith. Lyon Township residents deserve to know what is available to them, and we remain ready to have that conversation with the Board whenever they are ready.”

Several members of Lyon Township’s board did not respond to inquiries from Crain’s.

Local resistance

The project has stirred controversy throughout the year as an anti-data center movement has swept Michigan, and the nation writ large.

The development includes 1.8 million square feet of data center space in six buildings on 172 acres on Grand River Avenue between Milford and South Hill roads on the north side of the small Oakland County township.

Detroit-based Walbridge is the owner of the property and the general contractor for the build-out of the center, which is adjacent to several of their developments in the South Hill Business Park.

The project received conditional site plan approval from the township’s planning commission in September but ran into roadblocks in early 2026 as public sentiment on data centers shifted.

Angry residents filled South Lyon East High School in late January to oppose the project during a public informational meeting hosted by the township alongside Verrus, Walbridge and utility DTE Energy.

The Lyon Township board — now facing a citizen-led recall effort — then voted unanimously in May to deny an easement for a stormwater project adjacent to the property. The move effectively stopped Walbridge and developer Verrus from moving forward with thedata center that’s targeting California-based Anthropic, the maker of Claude, as its end user.

It was an about-face for the trustees, who have approved all other easements for developments at Walbridge’s South Hill Business Park off of Grand River Avenue where Walbridge wants to build the data center. Walbridge and the Oakland County Water Resource Commission were seeking an easement on 50 feet of township land for a drain bypass for stormwater management.

The project does not require approval from the full township board because data centers are a permitted use on the property zoned for light industrial and general industrial use. Lyon Township approved zoning for data centers in 1992. However, the planning commission still has to review a site plan to ensure it complies with township ordinances. That review was set for July 13, but Verrus asked to be withdrawn from the agenda, according to township staff.

Verrus, in a letter to the township board, has threatened potential legal action over what it views as exclusionary zoning under the state’s zoning laws.

“The current delays are primarily driven by heightened political scrutiny and evolving community concerns rather than underlying fatal entitlement, utility, or land use defects,” Verrus wrote in an executive summary of the project in May. “Similar dynamics have occurred on multiple large-scale data center projects throughout Michigan and nationally, including projects that ultimately advanced through negotiated community frameworks and supplemental operational commitments.”

Looking to Google

Verrus is looking to Van Buren Township and its agreement with Google for another hyperscale data center project in the Southwest Wayne County community.

Van Buren Township’s Board of Trustees unanimously approved a lucrative local property tax incentive package for Google’s massive hyperscale data center project despite community pushback.

The contentious project is set to pay only half of the projected $250 million in total property taxes over 12 years after the board voted to approve the Industrial Facilities Tax exemption, which provides a 50% reduction in taxes for high-tech equipment investment. Google’s data center is expected to include up to $2 billion in computer hardware and related equipment in the three-building project in Van Buren Township, according to Google’s consultant on the project, W. Ford Graham of McGuire Woods.

Van Buren Township Supervisor Kevin McNamara told Crain’s the deal was a strategy to protect the community.

“We got painted into a corner and everyone knows that,” McNamara told Crain’s. “But we could have done what Saline (Township) did and make the courts tell us to do it and lose total control. They have no control, no negotiating power. Bulldozers were basically dropped the next day, no planning review, no nothing. With this deal, we get to maintain control … We did what we could do to protect this community.”

The data center is a three-building facility being planned on a 282-acre site near the interchange of interstates 94 and 275.

Like Lyon Township, the land in Van Buren Township is zoned for data centers, a designation that came long before hyperscale artificial intelligence data centers were ever conceived. Because of the zoning, the project is considered a “use by right” under the Michigan Zoning Enabling Act in 2006.

In contrast, the board of trustees for Saline Township, which is the site of Oracle’s massive hyperscale data project proposal, voted down a rezoning of some of the project site’s parcels and was quickly sued by the property owners, alleging exclusionary zoning practices. The township quickly settled before being dragged through a potentially long lawsuit against some of the most well-capitalized companies in the world.

Verrus believes an agreement on investment and ordinances is possible in Lyon Township.

“Verrus is evaluating a potential Memorandum of Understanding (“MOU”), similar in concept to the framework utilized in Van Buren Township, intended to consolidate community-focused commitments and provide a clearer political and procedural path forward for the township,” it wrote in its executive summary of the final site plan in May. “Many of the commitments currently under discussion have already been incorporated into the final site plan submissions and supporting technical materials. Formalizing those items through a broader community framework may help alleviate the political and public pressures currently contributing to the extended review timelines associated with Project Flex.”

Resolution or litigation?

The plea for a benefits agreement in Lyon Township comes before the planning commission meeting’s site plan review for the project. That meeting was initially scheduled for July 13, but the meeting was canceled after Verrus requested to be removed from the agenda.

“The project will not be considered at the July 13 Planning Commission meeting as Township staff and consultants complete their review of an updated site plan submission that incorporates the latest feedback,” Verrus said in a statement to Crain’s. “We remain confident the project will meet the Township’s requirements for approval and appreciate the continued collaboration throughout the review process. We look forward to presenting the project to the Planning Commission and continuing to work with the Township.”

And the developers and the township’s contracted urban planning firm, Northville-based McKenna and Associates, appear to be in opposition over the final site plan.

McKenna argued in a June 26 letter to the township that the project has outstanding zoning and site plan compliance issues that negate its original site plan, including raising the building height by two feet; adding water tanks and a pump house, a change in the lighting plan and missing information, among other concerns.

Verrus, through attorneys at Dykema, however, plans to stick to its submitted site plan for final approval, the McKenna letter read.

“The applicant’s supporting letters note that the 3rd submission is the ‘final submission’ of the plans to the Township, an indication that the plans will not be amended to comply with the Township’s ordinances and conditions of approval,” Brian Keesey, senior principal planner for McKenna, wrote in the letter to the board. “Upon confirmation that revisions are not planned, we recommend planning commission deny the site plan and rescind the original conditional approval based on the fact that ordinance compliance is not going to be achieved for the project.”

Verrus, however, disagrees and claims it is in compliance with the township’s ordinances.

“Verrus believes the record now objectively demonstrates compliance with the applicable zoning ordinance, technical standards, and conditions associated with the township’s prior conditional site plan approval,” it wrote in the executive summary. “Accordingly, Verrus believes final site plan approval is appropriate and warranted under the township’s ordinance and applicable Michigan law, and expects the township to proceed toward approval rather than continued iterative consultant review cycles or expanded review requests outside the scope of final site plan review authority.”

The planning commission could also delay a decision to give Verrus more time to alter its site plan. Or it could deny the plan altogether, scrapping the multi-billion dollar development.

Whether that lands Lyon Township in court in opposition to a well-capitalized tech company remains to be seen.

— Editor’s note: This story was updated Tuesday with new information regarding the status of Lyon Township’s July 13 planning commission meeting.

Recent Posts